Robust evidence of value of infrastructure procurement models essential to effective future investment

Published: 26 Jul 2019

By: NIC

Tagged:

Cars on a road

The procurement of infrastructure projects risks being constrained by lack of evidence on long-term investment outcomes and could have strategic implications for the UK’s ability to meet growing demand for infrastructure services and its Net Zero emissions targets.

The lack of a strong evidence base on infrastructure procurements has led to the focus on a single measure of performance, usually short-run cost. As a result, future procurement decisions risk being made on the basis of opinion and judgement, limiting the scope for lessons to be learned to improve future practice.

Launching a framework to assess private financing and traditional procurement, the National Infrastructure Commission today said results from the pilot showed the public sector must do more to understand the benefits and downsides of different procurement options and improve its project data management. Doing so will also address existing concerns about transparency and public accountability and improve the public sector’s chances of securing the private financing UK infrastructure will need up to 2050.

This analytical framework – tested in partnership with Highways England – provides a comprehensive tool for analysing the whole-life performance of different procurement models. It aims to ensure that government selection of infrastructure procurement models is made with a robust consideration of broader factors beyond cost.

Chair of the National Infrastructure Commission Sir John Armitt said:

“Thirty years ago, the UK led the way in infrastructure financing and with PFI and PF2 off the table, recapturing that innovative spirit is vital. But without an objective way to determine value, officials risk making decisions with one hand tied behind their back.

“Transforming the nation’s infrastructure means mobilising private sector investment alongside that of government. It’s imperative we develop the tools to make better decisions about what works and what doesn’t and address existing concerns about the use of private finance.

“That requires an honest conversation about the role it plays in supporting our infrastructure investment and the partnership models we need. This framework encourages the public sector to view data differently and ask the right questions to get the best taxpayer deal, whatever the procurement model.”

A robust evidence base supports long term value for money

The framework sets out best practice principles to assess any procurement model. By focusing on a broader assessment of outcomes in addition to cost and taking a whole life view, it aligns closely with the emphasis on quality infrastructure investment principles promoted by the Japanese 2019 presidency of the G20.

The framework proposes a more balanced understanding of the performance of private financing and traditional procurement. It builds upon past research that has focused solely on analysing performance in the construction phase of projects, and fills an existing gap in analytical tools.

The framework encompasses a wide range of criteria for success and is designed to better reflect the long-term nature of infrastructure assets. By using it, public procurers, private sector infrastructure operators, and scrutiny bodies will be able to develop a more comprehensive understanding of performance over the lifetime of infrastructure assets, that takes into account factors including:

  • Asset build quality and condition
  • Quality of service
  • Wider outcomes, including social and environmental factors.

The Commission piloted the framework in collaboration with Highways England, applying it to five road projects, three completed under private financing and two by traditional procurement. Feedback from the independent advisory group set up to provide challenge to the Commission’s work identified no significant gaps in the framework’s design, and proposed a number of areas for further refinement.

Removing doubts about the right procurement model

The pilot found limited data on public financed projects, which is in part due to the age of some of projects used. This means developing a robust evidence base of costs and benefits of private finance and traditional procurement using roads projects alone is not achievable in short term. In addition, data aggregation at a regional makes it difficult to identify project specific data.

These findings support the Commission’s National Infrastructure Assessment recommendation that data on major infrastructure project costs and performance at each appraisal stage and upon completion should be collected as a matter of course. Adoption of the framework would give the UK a global lead in the analysis and benchmarking of infrastructure procurement.

The Commission will now explore the opportunity to apply the framework in other infrastructure sectors, generating further insights on data availability on public financed projects and to enhance the effectiveness of the analytical framework as an evaluation tool. It is encouraging a wide range of government departments, scrutiny bodies, operators and investors to adopt and apply the framework to generate more balanced evaluation of investment outputs and wider outcomes, and as a tool to supplement project appraisal consideration.

Notes

  • The report Evaluating the Performance of Private Financing and Traditional Procurement is available on the Commission’s website
  • The proposal for an analytical framework infrastructure for whole-life evaluation came out of the National Infrastructure Assessment. It identified the need for a better understanding of the costs and benefits of private financing and traditional procurement in the delivery of publicly funded infrastructure projects
  • The Highways England roads projects used in the framework pilot evaluation were A419/417 Swindon to Gloucester; M1/A1 Bramham to Lofthouse Link; A1 Darrington to Dishforth; A1 Dishforth to Leeming; A43 Improvements

 

Share this article

<

Recent Articles

Coming up in 2024
Thumbtack pins in calendar concept for busy, appointment and meeting reminder

Coming up in 2024

This page shows a calendar reflecting the latest expected dates for Commission reports, publications and events. You can also sign up to receive our quarterly newsletter by entering your email address in the box at the foot of each website page.

1 Feb 2024 By
Winser: NAO call for robust plan to boost low carbon heating “absolutely right”
picture of a heat pump by a wall

Winser: NAO call for robust plan to boost low carbon heating “absolutely right”

A National Audit Office report out today (18 March 2024) says heat pump installations are falling well below the level needed to meet the government’s targets of 600,000 units installed each year by 2028. The NAO says in response that a more robust plan from government and greater clarity on the future role if any...

18 Mar 2024 By
Government response on surface water flooding risk “does not meet scale of challenge”
A car splashes through a flooded Farringdon Lane in central London after a day of heavy rain.

Government response on surface water flooding risk “does not meet scale of challenge”

The government has today (13 March 2024) responded to the Commission’s study on reducing the risks of surface water flooding, published in November 2022. While it accepts the principles behind a number of the Commission’s recommendations, the government’s response – in the Commission’s view – makes few new commitments on steps to manage surface water...

13 Mar 2024 By
James Heath: urgent planning reform needed to remove “binding constraint” on UK’s economic future
A modern bridge over a dual carriageway cutting through British farmland

James Heath: urgent planning reform needed to remove “binding constraint” on UK’s economic future

James Heath, chief executive of the National Infrastructure Commission, spoke at the Nationally Significant Infrastructure Projects Forum in London yesterday (6 March). James offered the Commission’s view on the vital importance of speeding up the planning regime for major projects, given the need for pace in delivering tens of billions of pounds’ worth of schemes...

7 Mar 2024 By

Evidence_Icon_Turquoise Created with Sketch.

Explore data used in the Commission's research, and gain insights from across UK infrastructure

Join our team of professionals supporting the Commission to provide evidence based and forward thinking advice on infrastructure strategy.